Commercial

Business Bay Tower — Car Park Structural Repair

Diagnostic survey and full structural refurbishment of a five-level car park suffering chloride-induced reinforcement corrosion.

Client requirement

What the client needed

Arrest ongoing deterioration, restore the deck's design life and keep at least 70% of parking bays available at all times.

Diagnostic survey and full structural refurbishment of a five-level car park suffering chloride-induced reinforcement corrosion. Our team surveyed the existing build-up, recorded the failure points and agreed a phased programme with the consultant so the commercial asset stayed fully operational throughout the works.

Location

Business Bay, Dubai

Scope

Concrete repair, PU deck coating & joints

Business Bay Tower — Car Park Structural Repair

Execution

How the works were sequenced

01

Mobilisation

Site set-up, HSE induction, access scaffolding and material staging completed within the first week.

02

Preparation

Removal of failed layers, mechanical preparation and substrate repair to the specified profile.

03

Installation

System applied in controlled sections with daily QA sign-off and thickness verification.

04

Testing

Flood and adhesion testing witnessed by the consultant prior to protection layers.

05

Handover

As-built drawings, warranty documentation and a maintenance schedule issued to the client.

Gallery

Site documentation

Before — Business Bay Tower — Car Park Structural RepairBefore

Condition recorded during the diagnostic survey.

After — Business Bay Tower — Car Park Structural RepairAfter

Completed system following testing and handover.

Outcome

Measured results after handover

Location

Business Bay, Dubai

Scope

Concrete repair, PU deck coating & joints

Area

9,200 m²

Duration

16 weeks

Next step

Have a similar requirement?

An engineer attends site within one working day, diagnoses the root cause and issues a written specification — no obligation.